Repair BEQ Walkway B-4310

The work included Demolishing and replacing an existing cantilevered beam supporting the 2nd floor walkway, and incidental related work. The requirements included hiring a structural engineer to evaluate and confirm the project scope, and provide a sealed brief...

Replace GRIT System WWTP, B4376

The work included modifying existing headworks, demolishing the two existing Pista Grit 270s, grit washer, communitor, associated piping, asphalt, force mains, scum holding tank, scum pump station and other miscellaneous items. New work included two new Pista Grit...

Filter Wash Water Reuse, WTP

The work includes a new pump station, force main, and all associated appurtenances, modifications to existing water basin, new polymer feed system, modifications to storm sewer system, new valve and meter vaults, turbidity meter, electrical work, modifications to...

ARRA, P-1357, Child Development Center

The work included new construction of a child development center with the necessary utility infrastructure and incidental related work, including playground equipment.