Exceeding Expectations for over a Decade
Portfolio
Replace Gasoline Dispensing System, BT-11
Completion Date: Oct 1, 2013 |
Bid Type: General Construction MACC |
Project Duration: 90 Days |
Status: Completed |
Contract NumberN40085-10-D-0260-0018
Project ManagerBlue Rock Structures, Inc., Brent Hartness,910-743-0505,bhartness@bluerockstr.com
OwnerNAVFAC Midlant, Keith Willis, 252-466-5312
LocationMCAS, Cherry Point, NC
DescriptionThe work includes the replacement of fuel dispensers (gasoline and diesel),
replacement of a submersible fuel pump, the addition of remote fuel pumps,
associated piping and electrical work, repairing the existing tank
monitoring system and incidental related work.