Repairs to B-1795 for EOD

Completion Date: Apr 15, 2013

Bid Type: General Construction MACC

Project Duration: 270 Days

Status: Completed


Contract NumberN40085-10-D-0260-0012

Project ManagerBlue Rock Structures, Inc., Justin Jones, (910) 743-0505, jjones@bluerockstr.com

OwnerNAVFAC Mid Atlantic, Mike Morgan, (252) 466-4709

LocationMCAS, Cherry Point, NC

DescriptionThe work includes a 6,780 SF Building 1795- constructed in 1968- and will be used by three (3) EOD units starting in late FY10 with continued used thereafter. This project will remove asbestos and will repair mechanical, electrical, and plumbing systems, replace roof, replace vault door, replace fire alarm, install wet pipe sprinkler system, repaint interior and exterior, replace floor coverings, replace/repair interior and exterior doors, and repair acoustical ceiling.